Projects

G.H. Dawe Expansion
City of red deer - 20201

Services Provided

  • excavation 
  • water mainline installation
  • sanitary mainline installation
  • storm mainline installation
  • water/sewer service installation (mainline to property)
  • material cycling/handling
  • backfill and compaction completion
  • catch basin/catch basin lead installation
  • sewer bypassing
  • manhole installation
  • pipe insulation installation
  • protection of existing utilities
  • change order execution
  • temporary water line setup/testing/commissioning/implementation/municipal service reinstatement
  • water/sewer system CCC testing (pressure testing, chlorination, flushing, sewer scoping) 

Highlights / Challenges

  • Working around shallow utilities and protecting their integrity and operation.
  • Work around existing, operational mainlines.
  • Deep excavations (to 8ft) and unfavourable ground conditions.
  • Coordinating with and working around multiple other contractors to ensure everyone remains safe and on schedule.
  • Large format bypass pumping.
  • Supply schools and recreation center with temporary water.